The electric fusion pipe fitting construction is one of the most reliable connection methods for plastic pipeline systems such as polyethylene (PE) and steel wire mesh skeleton plastic composite pipes. It uses an electrofusion welding machine to heat the resistance wire inside the pipe fittings, causing the plastic at the contact surface of the pipe fittings and the pipe materials to melt, thereby achieving a secure connection and forming a leak-free sealed joint.
However, electric fusion welding has extremely high requirements for the operating environment, pipe material processing, and parameter settings. A minor mistake can lead to "false welding" or "over welding", potentially causing huge safety hazards for the project.

 


The electrofusion pipe fittings supplied by Zhejiang Qingfa Pipe Industry Technology Company



The electrofusion pipe fittings (coupler, elbows, tee, reducers, etc.) we supply are compatible with PE water supply pipes, PE gas pipes, and steel wire mesh composite pipes. The main parameters are as follows:
Specification range: dn50 to dn1600, covering the entire series
Resistance wire: High-quality copper-coated steel wire, with stable resistance value and uniform welding heat
Observation holes: Built-in spring type or plunger type, automatically protrude upon complete fusion, intuitive and reliable
Barcode system: Each pipe fitting comes with a unique welding barcode. Scanning the barcode automatically matches the parameters, eliminating human errors.

 


The complete construction steps of electrofusion pipe fittings

Checks Before Construction


1. Before construction

check the specifications: the materials of the pipes and pipe fittings (PE100/steel wire mesh core), pressure grade, nominal diameter (dn), and SDR series must be consistent.

Pipe fitting inspection: the appearance of the pipe fittings should be free from damage, the copper wire should be free of oxidation, the barcode should be clear and scanable; the observation hole spring should be free of rust.

Environmental temperature influence:

when the environmental temperature is lower than 5℃, preheating treatment should be carried out on the pipes and pipe fittings before welding. The preheating temperature is generally controlled at 20-30℃. Electric heating strips, insulation sheds or warm air blowers can be used for preheating. When the environmental temperature is lower than -5℃ or higher than 45℃, with humidity > 90% and wind speed > 8m/s, a wind shelter, insulation shed or other temperature control measures must be set up.

Welding in the open air under rainy or snowy weather is strictly prohibited.

Pipe Material Processing And Cutting

2. Pipe material processing (key step) Cutting: Use a planetary cutting machine or a dedicated rotating cutter to ensure that the pipe end face is perpendicular, with a perpendicularity deviation of ≤ 0.5mm. Do not cut randomly with a hand saw.
Cleaning: Before construction, the pipe material and pipe fittings must be strictly cleaned to remove impurities such as oil, dust, and moisture from the surface. Use a dedicated cleaning agent and wipe clean with a clean cloth.
Scraping the oxide layer:
Use a scraper or an angle grinder (with a dedicated scraping head) to remove the oxide layer from the outer surface of the pipe material, with a depth of 0.1 to 0.2mm. The surface should feel smooth.
The scraping length should be 10 to 15mm longer than the socket depth of the pipe fitting to ensure that there is no oxide layer in the entire socket area.
Secondary cleaning: After scraping, wipe with isopropyl alcohol to ensure there are no dust or oil stains. Do not touch with your hands after cleaning.

Marking And Insertion Depth

3. Marking and Insertion
Marking insertion depth: The insertion depth should be no less than the marking depth of the pipe fitting's socket (usually the pipe length minus 5mm). Use a marker pen to draw a circular line on the pipe material.
Insertion: Insert the electric fusion pipe fitting into the pipe material up to the marking line, maintaining the concentricity of the pipe and the pipe fitting and avoiding eccentricity (eccentricity ≤ 0.3mm). Special measuring tools can be used to ensure the insertion depth and concentricity.
Fixation: For large-diameter pipe fittings (dn ≥ 315), when welding, both ends of the pipe material must be fixed with fixtures or shims to prevent insertion deviation or displacement caused by welding thermal expansion.

Welding Parameter Settings: Scan And Automatic Mode

4. Welding Parameter Settings
Scan and Automatic Mode (recommended): Use the electric fusion welding machine to scan the barcode of the pipe fitting, and the welding machine will automatically read parameters such as welding voltage, power-on time, and cooling time.
Manual Input Mode: If there is no barcode or the barcode is damaged, the parameters must be manually input according to the technical manual provided by the manufacturer. Example (for reference only, based on the actual pipe fitting):
Dn110 PE electric fusion pipe fitting: Welding voltage approximately 39.5V, welding time approximately 120-150 seconds; dn250 SDR11 PE pipe: Voltage 39.5V, time 118 seconds, cooling 600 seconds
Some steel wire mesh reinforced pipe fittings: Voltage 17V, time 160 seconds
Connection Electrode: Firmly clamp the welding machine output line clamp onto the pipe fitting terminal, and do not loosen it.
Start Welding: After confirming the parameters, start the welding. During the welding process, do not move the welding machine, the pipe material, or touch the joint.

Monitoring During The Welding Process

5. Monitoring during welding process
During the welding process, pay attention to checking whether the display parameters of the welding machine remain stable. For some pipe fittings, observe whether the surface temperature is uniform.
If any abnormalities are detected (such as sudden change in current, smoke coming from the pipe fitting, etc.), immediately stop the welding and investigate the cause.
6. Cooling
Once the welding process is completed as indicated by the welding machine, the cooling countdown begins. The cooling time varies depending on the size of the pipe fittings: Small diameter pipe fittings (dn ≤ 110): The cooling time is approximately 10 to 15 minutes.
Medium diameter (dn 200): The cooling time may require 20 to 30 minutes.
Large diameter (dn ≥ 315): The cooling time is usually ≥ 40 minutes. During the cooling period, it is strictly prohibited to move the pipe material, apply force, or touch the joint. Forced cooling with water is not allowed.

Visual Inspection After Welding

7. Visual Inspection
After the electrofusion pipe fittings are welded, a visual inspection must be conducted:
Check the observation holes: The height of the cylindrical protrusion should be ≥ 10mm (or the value specified by the manufacturer). If there is no protrusion or the protrusion is not obvious, it is considered a failed fusion and needs to be cut and re-welded.
Check for any defects such as bubbles, cracks, or deformation at the welding area.
For areas with minor defects, they can be treated using repair methods (such as re-welding with a heat gun), but this should be done with caution; if the defects are severe (such as obvious cracks, large areas of bubbles), they must be cut and re-welded.
Use a wooden hammer to gently tap the reinforcement part of the pipe body. A clear sound indicates qualification; a dull sound may indicate incomplete welding.

Pressure Test After Construction

8. Pressure Test (After Construction) After the construction is completed, a pressure test must be conducted on the connection parts of the electrically fused pipe fittings to ensure the safety and reliability of the pipeline system.
Test pressure: Generally, it is 1.5 times the working pressure of the pipeline.
Pressure holding time: No less than 10 to 15 minutes.
Judgment: If there is no leakage at the welding parts and around the pipe fittings, it is considered qualified. If there is leakage, the pressure needs to be released, the cause needs to be investigated, repaired or re-welded, and then the test needs to be conducted again.

 

Coupler Electrofusion

 

Need A Welding Machine You Can Rely On Site?

Zhejiang Qingfa Pipe Technology Co., Ltd. has manufactured PE pipe fittings since 1999, covering 65 product families from dn20 to dn1200 with ISO 9001, ISO 14001 and ISO 45001 certification, ECM approval and a CNAS-accredited in-house laboratory. Send us your specification and our team will come back with a quotation and the test documentation your project needs.

Zhejiang Qingfa Pipe Technology Co., Ltd. · www.qingfaindustry.com · +86 151 6813 1515

Send Inquiry