HDPE Butt Fusion Parameters: DVS 2207-1 Table and Calculator

Nov 11, 2026

Leave a message

Butt fusion is a five phase process and every phase has a number attached to it, but the numbers come from two different places. The times and the alignment gap come from the wall thickness, through a table in DVS 2207-1 or the equivalent clause in ISO 21307. The pressure the machine holds comes from the interface area of the two pipe ends and the specific joining pressure of 0.15 N/mm². Get one and not the other and the joint is out of specification even when the machine did exactly what it was told.

The calculator below takes a pipe size and returns the whole parameter set for the single low pressure procedure, including the force the carriage has to apply and the gauge reading that force corresponds to on a given machine.

Fusion parameters for one joint

Single low pressure procedure, heater face 200 to 220 °C. Values follow DVS 2207-1 Table 2.

Enter a pipe size to see the parameter set.
Wall thickness
-
table row
Heat soak time
-
10 x wall
Changeover, max
-
seconds
Cooling under pressure
-
minutes, minimum
Joining force
-
kN at 0.15 N/mm²
Gauge reading
-
bar, before drag

Two fields in the calculator are usually left blank and should not be. The ram diameter decides how much force a bar of oil pressure produces, and it differs between machines of the same nominal size - a 315 machine from one maker can need a visibly different gauge reading for the same joint than another maker's. The drag pressure is the pressure needed to move the carriage before the pipe ends touch at all, and it has to be measured on the day, because it changes with the weight of the pipe and the condition of the rams.

The five phases, and which number belongs to each

Facing is the phase with no pressure: the ends are machined flat and parallel, and the only number that applies is the alignment gap. Bead-up presses the two faces against the heater at the joining pressure until a continuous bead has formed around the circumference. Heat soak drops the pressure to almost nothing - the contact pressure, not the joining pressure - and holds it while heat travels through the wall. Changeover removes the plate and brings the ends together, and it is the phase where time matters more than force. Joining applies the joining pressure again and holds it while the bead rolls back. Cooling keeps that pressure on until the joint is strong enough to take a load.

Interface pressure through the five butt fusion phases: bead-up at 0.15 N/mm2, heat soak at about 0.01, changeover at zero, then joining and cooling at 0.15
Two 0.15 plateaus, set by two different controls.

The heat soak time in the table is not an independent number: it is ten seconds per millimetre of wall, which is why the table rows read 45, 70, 120, 190, 260, 370, 500 and 700 seconds across the wall bands. The cooling time follows a similar rule at roughly 1.2 minutes per millimetre, and it is the phase most often cut short on site when the weather turns or the shift ends. A joint released early does not fail visibly; it fails later, usually as a brittle crack running out of the fusion zone.

The DVS 2207-1 parameter table

The table below is the single low pressure series for PE. The alignment figure is the maximum offset between the two faced ends at the joint, and the times are the ones the standard tabulates; the ranges exist because a wall thickness sits inside a band rather than at a point.

Wall, e (mm) Alignment gap (mm) Heat soak (s) Changeover (s) Build-up (s) Cooling (min)
up to 4.50.545556
4.5 to 71.045 to 705 to 65 to 66 to 10
7 to 121.570 to 1206 to 86 to 810 to 16
12 to 192.0120 to 1908 to 108 to 1116 to 24
19 to 262.5190 to 26010 to 1211 to 1424 to 32
26 to 373.0260 to 37012 to 1614 to 1932 to 45
37 to 503.5370 to 50016 to 2019 to 2545 to 60
50 to 704.0500 to 70020 to 2525 to 3560 to 80

Above 70 mm of wall the single low pressure series stops being the right procedure: the heat has to travel further than the phase times allow, and the dual pressure or the high pressure variant takes over. That is a procedure decision, not a calculator setting, and it belongs to whoever wrote the welding procedure specification for the project.

0.15 N/mm² is an interface pressure, and the dial reads oil

The force to join two pipe ends is the specific joining pressure multiplied by the annular area of the interface, which is pi times the wall times the mean diameter. For DN315 SDR11 the annulus is about 25,700 mm², so the carriage has to deliver roughly 3.9 kN. On a machine with an 80 mm ram that is about 7.7 bar of oil pressure, and the same joint on a machine with a 100 mm ram needs about 4.9 bar.

That conversion is where most parameter sheets stop being useful, because the number written on a gauge is a property of the machine and not of the joint. Add the drag pressure, measured with the carriage closed on nothing, and the set point for the day is complete. The machine calibration routine covers how to measure drag and how to check that the gauge is telling the truth before it is trusted.

Where these numbers stop applying

Three situations take the table out of scope. The first is a cold site: below about minus five degrees the heater has to work against a much larger heat sink, and most procedures require the pipe ends to be sheltered and the cycle times extended or the joint postponed. The second is a different polymer - polypropylene runs hotter and needs its own table, and mixing the two series is how joints get made at the wrong temperature. The third is a machine that holds pressure badly: a leaking ram produces a joint pressed at the right pressure for the first ten seconds and the wrong one afterwards, which visual inspection will not catch.

Electrofusion sits outside all of this. The fitting carries a barcode or a printed parameter set and the control box runs the cycle itself, which is why the discipline there is about scraping, clamping and cooling time rather than about pressure arithmetic. The electrofusion fittings page covers that sequence, and the standards comparison sets out how DVS 2207 and ISO 21307 divide the same job between a national code and an international procedure.

What belongs on the weld record

A parameter table is only useful if the joint can be shown to have followed it. The record that survives an audit is short, and it is the same four lines whether the project is a municipal water main or a gas distribution network. Without them a joint is either accepted on the strength of its bead, which proves very little, or cut out.

  • The four numbers. Diameter, wall thickness, SDR and the material grade of both ends. They establish that the two pipes belong to the same system, which is the failure mode that no amount of pressure discipline can rescue.
  • The machine and its set point. Machine identifier, ram diameter, the drag pressure measured that shift, and the gauge reading actually used. A gauge figure with no ram diameter beside it cannot be checked afterwards.
  • The cycle as it ran. Heater temperature, heat soak time, changeover time and the time the joint stayed clamped under pressure. On a data-logging machine this is automatic, and the log is the reason those machines cost more.
  • Who made it. Operator name and qualification reference. Welder qualification is a separate document from the procedure, and a project that asks for one usually asks for the other.

Two of those fields are worth more than the rest. The changeover time is the phase most often exceeded and least often recorded, and the cooling time is the phase most often shortened under schedule pressure. Both are visible in a log and invisible in a photograph of the bead, which is why an inspection that stops at the bead is not really an inspection.